JGW-G1910901-v2

DocDB Home ]  [ Search ] [ Recent Changes ]

Future Plans of Ground Based GW projects (地上の将来計画)

Document #:
JGW-G1910901-v2
Document type:
G
Submitted by:
Sadakazu Haino
Updated by:
Sadakazu Haino
Document Created:
24 Oct 2019, 17:06
Contents Revised:
18 Dec 2019, 19:16
DB Info Revised:
19 Dec 2019, 23:31
Viewable by:
Modifiable by:
Other Versions:
JGW-G1910901-v6
08 Sep 2022, 20:21
JGW-G1910901-v5
08 Sep 2022, 18:33
JGW-G1910901-v4
28 Dec 2019, 02:49
JGW-G1910901-v3
21 Dec 2019, 08:57
Abstract:
Talk which will be given in CRC town meeting on Dec./21, 2019
http://www.icrr.u-tokyo.ac.jp/CRC/townmeeting/tm20191220_program.pdf

(English Translation)
We have finished all the optical system of KAGRA and now we are in a commissioning phase to join the 3rd observation (O3) with LIGO and Virgo. In this talk, we will discuss about upgrade plans for O5 planned around 2024 and ultimate configuration toward 2030's.

(Original Japanese)
KAGRA 重力波望遠鏡は光学系のインストールが完了し、 LIGO、Virgo との第3次共同観測(O3)に参加するためにコミッショニングを進めている。本発表では、2024 年頃に予定されている第5次共同観測(O5)と、2030 年以降に向けた究極的なアップグレードプランについて議論する。
Files in Document:
  • slides (GWground.pdf, 23.0 MB)
Keywords:
KAGRA upgrades
Referenced by:
  • JGW-G2012047: FPC report for PAB
  • JGW-P2214531: Application of Future Science Promotion Concept (未来の学術振興構想)
DocDB Home ]  [ Search ] [ Recent Changes ]

DocDB Version 8.7.10, contact Document Database Administrators